Job # Status Building Category Description Remarks
    Campus UTILITIES UTILITY INFRASTRUCTURE AND CEP UPGRADES  
08-01744 COMPLETE Campus UTILITIES 2008 STEAM SHUTDOWN  
09-01841 DESIGN Campus UTILITIES DEVELOPMENT DRAWINGS FOR UTILITY RENOVATIONS & UPGRADES  
08-01749 COMPLETE Fine Arts UTILITIES INSTALL RECORDABLE FLOW METER  
09-01884 CONST CEP UTILITIES REPLACE CHILLER Re-bidding chiller
09-01870 CONST Campus UTILITIES INFRARED SCANNING MECH/ELEC EQUIPMENT  
09-01852 COMPLETE Campus UTILITIES INSTALL SURGE PROTECTION  
08-01641 DESIGN Campus UTILITIES INSTALL CAMPUS & BUILDING UTILITY METERING SYSTEM  
09-02016 CONST Campus UTILITIES TRANSFORMER EVALUATION/REBUILDING AND REPLACEMENT  
    Campus ADA OCR REVIEW ITEMS  
09-01854 CONST Stadium ADA ADA COMPLIANCE  
09-01991 CONST Arena ADA ADA COMPLIANCE  
09-01856 CONST Wyo Hall ADA ADA COMPLIANCE - DOORWAY  
    Campus ROOFING ROOF REPLACEMENTS  
09-01917 DESIGN Campus ROOFING 2009 LOW SLOPE ROOF REPAIR AND REPLACEMENT   
09-01920 CONST Campus ROOFING 2009 STEEP SLOPE ROOF REPAIR REPLACEMENT   
    Stadium STRUCTURAL RECONSTRUCT STRUCTURAL FRAME  
09-01781 CONST Campus SECURITY SECURITY SYSTEM IMPLEMENTATION  
    Student Health MISC SUPPLEMENT FACILITY RENOVATION  
    Campus MISC PHYSICAL PLANT SPECIAL PROJECTS  
    Campus MISC ITEMS IDENTIFIED BY ACADEMIC AFFAIRS  