2007 Major
Maintenance Projects
Updated 12/17/2007
Contact
Mark Shively at 307-766-2537 with questions.
List of 2005 Major Maintenance projects: 2005 MM
List of outstanding Major Maintenance projects:
Outstanding MM
| Job # | Building | Category | Status | Description | Remarks |
| 07-01034 | Campus | ELEVATOR | CONST | INTERNAL PHYSICAL PLANT ELEVATOR REPAIRS | |
| Campus | HVAC | INTERNAL PHYSICAL PLANT HVAC PROJECTS | |||
| 10724 | Engineering | HVAC | COMPLETE | MODIFY AIR COMPRESSOR | |
| 07-01089 | Campus | HVAC | CONST | HVAC EQUIPMENT UPGRADES | |
| 07-01074 | Law School | HVAC | CONST | REPLACE COOLING COILS | |
| 07-01070 | Plant Science Green House | HVAC | CONST | REPLACE BOILERS | Boiler flue & control modifications |
| 07-01075 | State Vet Chem. Lab | HVAC | COMPLETE | REPLACE BOILER FLUE | |
| Campus | MISC. | DESIGN | INTERNAL PHYSICAL PLANT SPECIAL PROJECTS | ||
| 10721 | Physical Sciences | ELECTRICAL | COMPLETE | CORRECT ACCESS TO ELECTRICAL VAULT | |
| 08-01184 | Upholstery Shop | MISC. | CONST | FACILITY UPGRADE | finish by end of week 9/28 |
| 08-01215 | Education | CONCRETE | COMPLETE | REMOVE STAIRS NORTH OF EDUCATION AND LANDSCAPE | |
| 10722 | Biochemistry | CONCRETE | COMPLETE | REPLACE TRENCH DRAIN GRATING | |
| 07-01049 | Campus | CONCRETE | COMPLETE | DAY LOT RETAINING WALL REPAIR | |
| 10808 | Engineering | INTERIOR | COMPLETE | REPLACE WINDOW COVERINGS IN PETROLEUM WING | |
| 07-01095 | State Vet Chem. Lab | DOOR | COMPLETE | REPLACE ROLLING SERVICE DOOR | |
| 07-01096 | Day Care | CONCRETE | COMPLETE | REPAIR CONCRETE AND IRRIGATION SYSTEM | |
| 07-01086 | Half Acre Pool | PLUMBING | COMPLETE | REWORK DRAIN AND FILTERING SYSTEMS, REPAIR POOL TILE | |
| 07-01083 | Campus | ELECTRICAL | COMPLETE | CLEAN AND REPAIR MEDIUM VOLTAGE SWITCHES. | |
| 08-01264 | Engineering | PAINTING | COMPLETE | PAINT & REFINISH HANDRAIL | Complete hand rail and doing entry wall |
| Campus | ROOFING | CONST | INTERNAL PHYSICAL PLANT ROOFING MAINTENANCE PROJECTS | Contract with Big Horn Roofing | |
| 10713 | Campus | ROOFING | COMPLETE | CONTRACTOR MAINTENANCE AND REPAIR | |
| 07-01056 | Corbett | ROOFING | CONST | REPLACE ROOFS A E F & G | |
| 07-01054 | Health Sciences | ROOFING | COMPLETE | REMOVE AND REPLACE ROOF | Reviewing final bills |
| 07-01064 | Campus | ROOFING | CONST | FY 07 ROOF CONTRACT | |
| 07-01055 | Classroom building | ROOFING | COMPLETE | REPLACE OVERFLOW DRAINS | |
| 08-01279 | Agronomy Farm | ROOFING | CONST | REPLACE ROOF | Project Bid |
| Campus | SHUTDOWN | COMPLETE | ANNUAL STEAM DISTRIBUTION REPAIRS | ||
| 10668 | Campus | SHUTDOWN | COMPLETE | 2006 ANNUAL STEAM DISTRIBUTION REPAIRS | |
| 10690 | Campus | SHUTDOWN | COMPLETE | 2006 ANNUAL STEAM DISTRIBUTION REPAIRS | |
| 07-01099 | Campus | SHUTDOWN | CONST | 2007 ANNUAL STEAM DISTRIBUTION REPAIRS | Insulator and asbestos contractor |
| Campus | UTILITIES | NEW | INTERNAL PHYSICAL PLANT UTILITY PROJECTS | FY08 Upgrades | |
| 07-01029 | Pharmacy | UTILITIES | COMPLETE | REPLACE VACUUM SYSTEM | Complete Oct. 1, then billing |
| 07-01041 | Bio Sciences | PLUMBING | COMPLETE | REPLACE HOT WATER HEATERS | |
| 07-01042 | Service Building | UTILITIES | COMPLETE | REPLACE PRV STATIONS | |
| 07-01036 | Wyo Vet Lab | CONTROLS | CONST | REBUILD AIR COMPRESSORS | |
| 10773 | McWhinnie | UTILITIES | COMPLETE | ABATE UTILITY TUNNEL | |
| 07-01102 | CEP | UTILITIES | COMPLETE | REPLACE TURBO ON GENSET | |
| 07-01122 | Campus | UTILITIES | COMPLETE | INFRARED SCAN EQUIPMENT | Phase 2 complete |
| Campus | ADA | NEW | PROJECTS IDENTIFIED IN ADA STUDY/ACCESS REPORT | Prioritizing FY08 projects | |
| 10793 | Health Sciences | ADA | COMPLETE | CORRECT OCR ISSUES | |
| 07-01119 | Casper Fam. Practice | ELEVATOR | CONST | ADA UPDATES | |
| 07-01023 | Campus | ELEVATOR | CONST | REPAIR AND REPLACE ELEVATOR CARS AND CONTROL | |
| 07-01079 | Campus | ELEVATOR | SCHEDULING | GROUND ELEVATOR SHAFTS | Quality Electric |
| Campus | MISC. | DESIGN | EMERGENCY REPAIRS | ||
| 07-01043 | Fieldhouse | INTERIOR | COMPLETE | REPLACE EXISTING BLEACHERS | |
| 08-01127 | Classroom Building | ELECTRICAL | COMPLETE | REPLACE EMERGENCY GENERATOR | |
| 08-01251 | Centennial Complex | PLUMBING | CONST | RENOVATE DOMESTIC HOT WATER HEATER | Insulating |
| 08-01212 | Earth Sciences | PLUMBING | COMPLETE | REPLACE VFDS FOR PUMPS P5 AND P6 ON THE HEATING SYSTEM | Waiting on contractor, CFM |
| 08-01176 | Williams Conservatory | PLUMBING | CONST | REBUILD PROCESS COOLER | |