Building Project Description Request Date Estimated End Date
ADMIN OFFICE ANNEX BLDG (OLD FARM BUREAU 08-01213 CHANGE HARDWARE ON DOORS TO INCLUDE PANIC BARS: OFFICE ANNEX 205 8/7/2007  
ADMIN OFFICE ANNEX BLDG (OLD FARM BUREAU 08-01280 CONNECT UPS TO POWER LINE: OFFICE ANNEX SERVER RM 9/26/2007  
ADMIN OFFICE ANNEX BLDG (OLD FARM BUREAU 08-01365 INSTALL FENCING FOR STORAGE SPACES: OFFICE ANNEX BASEMENT 11/12/2007  
ADMIN OFFICE ANNEX BLDG (OLD FARM BUREAU 08-01689 REPLACE HOT WATER BOILER IN BASEMENT MECH RM OFFICE ANNEX 6/9/2008  
AGRICULTURE C 07-01002 REPLACE BRANCH CIRCUIT PANELS: AG C 6/27/2007  
AGRICULTURE C 07-01105 DESIGN LYSIMETER LAB: AG 1020 6/30/2007  
AGRICULTURE C 08-01167 MOUNT PROJECTORS: AG C 316 7/18/2007  
AGRICULTURE C 08-01373 VENTILATION WIRING & GAS SUPPLY MODIFICATIONS FOR NEW ICP INSTRUMENTATION: AG C 48 11/26/2007  
AGRICULTURE C 08-01403 REMOVE CHALK BOARD AND PAINT WALL: AG 20 1/15/2008  
AGRICULTURE C 08-01404 REMOVE PIPES SOUTH WALL NEAR DOOR: AG 20 1/16/2008  
AGRICULTURE C 08-01420 INSTALL ELECTRICAL OUTLET IN FACULTY RESEARCH LAB: AG 241 1/28/2008  
AGRICULTURE C 08-01494 BUILD WALL: AG C 229 3/17/2008  
AGRICULTURE C 08-01536 INSTALL DROP CEILING IN CLASSROOM: AG C 237 4/13/2008  
AGRICULTURE C 08-01570 RM 4040 INSTALL ACOUSTICAL CEILING AG C 4/30/2008  
AGRONOMY FARM HORSE BARN 08-01279 REPLACE ROOF: AGRONOMY FARM BARN 9/26/2007 7/31/2008
AGRONOMY FARM PROPERTY 08-01529 REPLACE PLANKING & BEAM: STOCK FARM BIG BARN 4/10/2008  
ALUMNI HOUSE 08-01216 ESTIMATE COST & TIME TO INTALL A/C& REVIEW HEATING: ALUMNI HOUSE 8/10/2007  
ANIMAL SCI/MOLECULAR BIOLOGY 08-01133 INSPECT AIR HANDLING SYSTEM: ANIMAL SCI 200 200A 200B 7/3/2007  
ANIMAL SCI/MOLECULAR BIOLOGY 08-01195 UNINSTALL AND REMOVE TWO AUTOCLAVES: ANIMAL SCI 208 & 209 7/31/2007  
ANIMAL SCI/MOLECULAR BIOLOGY 08-01732 INSTALL CEILING PROJECTOR WITH ELECTRICAL MOLEC BIO 6/25/2008  
ANIMAL SCI/MOLECULAR BIOLOGY 08-01733 REPLACE AUTOCLAVE AG C 6/25/2008  
ANTHROPOLOGY 08-01635 NO PARKING SIGNS ON NORTH SIDE OF LEWIS ST AT 6:00 AM MONDAY JUNE 9 FOR DELIVERY OF MILLWORK. NEED ENOUGH ROOM FOR A SEMI TRUCK ANTHROPLOGY 5/19/2008  
ANTHROPOLOGY 08-01636 ELECTRICIAN ASSIST IN CONNECTING POWER AND LIGHTING FOR NEW DISPLAY CASES IN CORRIDORS CASES WILL BE DELIVERED AND INSTALLED MONDAY JUNE 9. ANTHROPOLOGY 5/19/2008  
ANTHROPOLOGY 08-01715 ELECTRICIANS NEEDED TO SHUT DOWN FIRE ALARM TEMPORARILY WHILE FIRE SPRINKLER SYSTEMS IS BEING MODIFIED. KENT MARSHALL IS CONTRACTED TO DO MODIFICATIONS. WORK TO BEGIN AT 7:00 AM. WILL NEED ACCESS TO MECH ROOM ANTHROPOLOGY 6/18/2008  
ARENA AUDITORIUM 08-01230 EXTEND WALK OF FAME: ARENA AUDITORIUM 8/20/2007 3/30/2008
ARENA AUDITORIUM 08-01315 REPLACE LIGHTING & PAINT OUTER WALLS OF CONCOURSE ARENA AUDITORIUM 10/12/2007  
ARTS & SCIENCES 07-01018 UPGRADE SOUND SYSTEMS: A&S FINE ARTS ED AUDITORIUM 6/29/2007  
AVEN NELSON 08-01208 BUILD & INSTALL BOOKSHELVES: AVEN NELSON 107 8/7/2007  
AVEN NELSON 08-01418 PURCHASE AND INSTALL CORK BOARD & LOCKING POSTER CABINET AVEN NELSON 1/23/2008  
AVEN NELSON 08-01482 ABATE ASBESTOS: AVEN NELSON MECH ROOM 3/13/2008 6/30/2008
AVEN NELSON 08-01487 REMOVE SIGN ABOVE DOOR CHANGE SIGN ON DOOR: AVEN NELSON 138 3/13/2008  
BETA HOUSE 08-01722 DOOR SIGN ATTN JUSTIN ATTEBERY BETA HOUSE 6/20/2008  
BILL NYE AVE BLDG (PATTON & JOHNSON) 08-01725 SIGNAGE PROJECT BILL NYE 6/20/2008  
BIOLOGICAL SCIENCE 08-01359 REPLACE COUNTERTOPS INSTALL ELECTRICAL DOORS & FUME HOOD: BIO SCIENCE 323 11/6/2007  
BIOLOGICAL SCIENCE 08-01407 REMODEL LAB: BIO SCIENCE 206 1/16/2008  
BIOLOGICAL SCIENCE 08-01545 GLAZE BLOCK VENIER REPLACEMENT: BIO SCIENCE & PHYSICAL SCIENCE 4/16/2008  
BIOLOGICAL SCIENCE 08-01582 ADD A DOOR BETWEEN RM 20A AND MAIN LOBBY BIOLOGICAL SCIENCES 5/2/2008  
BIOLOGICAL SCIENCE 08-01596 RM 323 REPLACE SOME COUNTERTOPS/ INSTALL NEW DEDICATED ELECTRICAL LINES/ REMOVE FISH TANKS/PULL OUT OLD FUMEHOOD AND INSTALL NEW HOOD BIOLOGICAL SCIENCES 5/8/2008  
BUREAU OF MINES/WRI 08-01451 MODIFY WEST EXTERIOR FACILITY SIGN: WRI 2/27/2008  
CAMPUS GREENHOUSE 08-01728 RECONFIGURE STEAM PIT AND INSTALL SAFETY IMPROVEMENTS CAMPUS GREENHOUSE 6/23/2008  
CENTENNIAL COMPLEX 07-01038 REPLACE CHILLER: CENTENNIAL COMPLEX 6/30/2007 6/30/2008
CENTENNIAL COMPLEX 07-01045 REPLACE HEATING H2O PIPING: CENT CMPLX 6/30/2007 8/30/2008
CENTENNIAL COMPLEX 08-01196 INSTALL TEMPERATURE ALARM ON FREEZER: AHC KITCHEN 7/31/2007  
CENTENNIAL COMPLEX 08-01313 INSTALL LIGHTING EAST OF AHC 10/12/2007  
CENTENNIAL COMPLEX 08-01469 COOL SECURITY ROOM: CENTENNIAL COMPLEX 3/6/2008  
CENTENNIAL COMPLEX 08-01583 SECURE SHELVING TO WALL CENTENNIAL COMPLEX 5/2/2008  
CENTENNIAL COMPLEX 08-01637 DISABLE FIRE ALARM 5/19 & 5/20 CENTENNIAL COMPLEX 5/19/2008  
CENTENNIAL COMPLEX 08-01677 MOVE CENTENNIAL COMPLEX 6/5/2008  
CENTENNIAL COMPLEX 08-01679 PROVIDE 2 LABORERS W/ POWER WASHER W/ AN ADJUSTABLE PRESSURE GAUGE JUNE 10 @ 7:30AM CENTENNIAL COMPLEX 6/5/2008  
CENTENNIAL COMPLEX 08-01720 REPAIR HUMIDITY SYSTEM CENTENNIAL COMPLEX 6/19/2008  
CENTRAL ENERGY PLANT 07-01101 INSTALL ADDITIONAL SOOT BLOWER ON 2: CEP 6/30/2007  
CENTRAL ENERGY PLANT 08-01610 TEMPORARY CAMPUS COOLING FOR SUMMER FROM CHILLER #2 FAILURE 5/12/2008  
CLASSROOM 08-01301 INSTALL LOW VOLTAGE PROJECTION SCREEN CONTROL SWITCHES: CLASSROOM BUILDING 10/10/2007  
CLASSROOM 08-01378 SEWAGE EJECTORS: CLASSROOM 11/28/2007 5/30/2008
CLASSROOM 08-01388 MOUNT CAMERA ON WALL: CLASSROOM BUILDING 129 & 133 12/13/2007  
COE LIBRARY 08-01552 INSTALL PROVIDED SWIVEL CASTERS ON CHAIRS: COE 121 4/22/2008  
COE LIBRARY 08-01601 CLEAN MAIN AIR HANDLER COOLING COIL INCLUDING ACCESS PANEL INSTALLATION COE LIBRARY 5/9/2008  
COE LIBRARY 08-01650 REMOVE & RELOCATE OFFICE SIGNAGE COE 5/30/2008  
COE LIBRARY 08-01675 LOCK SHOP: RM 7 PROVIDE HARDWARE NEEDED TO SECURE SEE EXTRA DESC AND CALL SANDY FOR MORE DETAIL COE LIBRARY 6/5/2008  
COE LIBRARY 08-01699 CARPENTRY ASSISTANCE WITH LIBRARY MOVES INCLUDING REMOVAL OR RELOCATION OF WALL MOUNTED SHELVING - MARKER BOARDS - SIGNS - ETC COE LIBRARY 6/10/2008  
COE LIBRARY 08-01700 PROVIDE HARDWARE TO SECURE ROOM 7 COE LIBRARY 6/10/2008  
COE LIBRARY 08-01731 REPROGRAM COMBINATION LOCKS ON 6TH FLR COE LIBRARY 6/23/2008  
COE LIBRARY 08-01739 REMOVE *TESTING CENTER* FROM EXTERIOR SIGNS COE LIBRARY 6/26/2008  
CORBETT 07-01015 MOVE FORCE PLATES: CORBETT 120 6/29/2007 9/30/2007
CORBETT 08-01655 RM 120 HIGH VOLTAGE OUTLET CORBETT 5/30/2008  
CRANE HALL 08-01644 RM 103 BUILD CABINET/COUNTER CRANE 5/28/2008  
EARLY CARE & EDUCATION CENTER 08-01298 UPGRADE KITCHEN: EARLY ED CENTER 10/10/2007  
EARLY CARE & EDUCATION CENTER 08-01319 INSTALL CARD READER ON FRONT DOOR EARLY CARE & ED CENTER 10/15/2007  
EARLY CARE & EDUCATION CENTER 08-01449 CREATE SPACES FOR SHADE: EARLY CARE AND ED CENTER PLAYGROUND 2/27/2008  
EARTH SCIENCES 08-01179 EVALUATE AIR CONDITIONING SYSTEM: EARTH SCIENCE 2003 7/24/2007  
EARTH SCIENCES 08-01348 CHANGE OLD PERCHLORIC HOOD TO HF HOOD: EARTH SCIENCES ROOM 2015 11/5/2007  
EDUCATION 08-01183 PAINT AND CARPET: EDUCATION ROOMS 6 TO 11 7/26/2007  
EDUCATION 08-01314 INSTALL COVER ON STAGE PIT EDUCATION AUDITORIUM 10/12/2007  
EDUCATION 08-01456 REMODEL: EDUCATION 115 & 117 2/27/2008  
EDUCATION 08-01527 REMOVE SINKS: WYO HALL 409 412 417 4/9/2008  
EDUCATION ANNEX (VOCATIONAL) 07-01039 UPGRADE HEAT H2O PIPING: ED ANNEX 6/30/2007 8/15/2008
EDUCATION ANNEX (VOCATIONAL) 08-01674 CLEAN RESTROOMS AND CLASSROOMS /CONTRACTOR USED ED ANNEX 06/05/08 AND 6/6/08 6/5/2008  
ENGINEERING 08-01481 REMODEL LABS: ENGINEERING 1040 1038 1041 1039    
ENGINEERING 08-01506 FINALIZE PIRI LAB: EN 105B 6/27/2007  
ENGINEERING 08-01220 REPLACE WINDOWS: ENGINEERING L55&L65 8/20/2007  
ENGINEERING 08-01283 REMODEL LAB: ENGINEERING 4021 9/26/2007  
ENGINEERING 08-01285 INSTALL ELECTRICAL IN CEILING FOR MOUNTED PROJECTOR: ENGINEERING 1044 & 1045 9/26/2007  
ENGINEERING 08-01329 UPDATE ELECTRICAL IN FUME HOOD: ENGINEERING ROOM 2025 10/22/2007  
ENGINEERING 08-01332 REPAIR OR REPLACE BUILDING VACUUM PUMP: ENGINEERING BASEMENT MECH RM ENGINEERING ADDITION 10/24/2007 7/31/2008
ENGINEERING 08-01351 REMODEL KITCHENETTE: ENGINEERING 1060 11/6/2007  
ENGINEERING 08-01379 REPLACE LIGHT FIXTURES IN: ENGINEERING 2085 11/28/2007  
ENGINEERING 08-01485 HAND DIGITAL SIGN: ENGINEERING 2ND FL NW ENTRANCE 3/13/2008  
ENGINEERING 08-01528 PAINT & CARPET: ENGINEERING 5038 & 5031 4/9/2008  
ENGINEERING 08-01532 REMODEL OFFICE INTO WORKROOM & KITCHEN: ENGINEERING 2085A 4/11/2008  
ENGINEERING 08-01535 REMODEL ROOMS 1090 1075 1070 1074 1091 1092: ENGINEERING 4/11/2008  
ENGINEERING 08-01549 INSTALL LOCKS TO PREVENT ACCESS TO L31 FROM L40D & L30C: ENGINEERING 4/21/2008  
ENGINEERING 08-01550 REMOVE DOORWAY BETWEEN L31 & L40D ADD DOOR BETWEEN L31 & RAMP CORRIDOR: ENGINEERING 4/21/2008  
ENGINEERING 08-01555 IMPROVE LIGHTING FOR STUDY AREA: ENGINEERING 4/23/2008  
ENGINEERING 08-01586 REPLACE CARPETING AND PAINT WALLS ENGINEERING BLDG ROOMS 2034 AND 2068 5/5/2008  
ENGINEERING 08-01603 PAINT/ CARPET AND REMOVE AIR COND ROOM EN2079 A B C ENGINEERING 5/9/2008  
ENGINEERING 08-01609 CONNECT OVEN TO POWER ENGINEERING BLDG 5/9/2008  
ENGINEERING 08-01614 2 220 SINGLE PHASE 20 AMP CIRCUITS INSTALL ROOM 4042 ENGINEERING BLDG 5/13/2008  
ENGINEERING 08-01642 INSTALL WIRING FOR TWO LABORATORY OVENS IN RM 4014 ENGINEERING BLDG 5/28/2008  
ENGINEERING 08-01645 ROOM 2022:PAINT AND REPLACE CARPETING ENG BLDG 5/29/2008  
ENGINEERING 08-01654 RM 4021 REMODEL & ADD HOOD-SINKS-UTILITIES ENG BLDG 5/30/2008  
ENGINEERING 08-01661 RM 2085 NEW PIECE OF GLASS FOR DESK ENGINEERING BLDG 6/3/2008  
ENGINEERING 08-01685 RM 2100 ABATE TILE FROM STAGE ENGINEERING BLDG 6/9/2008  
ENGINEERING 08-01690 ATTN NORM/ ROOM 4024/ INSTALL THERMAL COUPLER MOHAMMAD HAS TALKED TO JOHN S ALREADY 6/9/2008  
ENGINEERING 08-01698 ELECTRICAL ASSISTANCE DURING FURNITURE INSTALL 6/16/08 @ 10AM ENGINEERING 2099 6/10/2008  
ENGINEERING 08-01701 INSPECT DUCT WORK ENGINEERING BLDG 6/12/2008  
ENGINEERING 08-01703 ROOM 4054/ MOUNT PROJECTOR AND SCREEN ENGINEERING BLDG 6/13/2008  
ENGINEERING 08-01717 RM 2111 RENOVATE INTO COMPUTER LAB ENGINEERING BLDG 6/18/2008  
FAMILY PRACTICE PROGRAM SITE 07-01119 ELEVATOR ADA UPDATES: CASPER FAMILY PRACTICE 6/30/2007 12/1/2008
FAMILY PRACTICE PROGRAM SITE 08-01311 ELEVATOR ADA REQUIREMENTS & PUMP REPLACEMENT CHEYENNE FAMILY PRACTICE 10/12/2007  
FAMILY PRACTICE PROGRAM SITE 08-01530 ASBESTOS ABATEMENT: CASPER FAMILY PRACTICE 4/10/2008  
FIELDHOUSE NORTH ADDITION 08-01461 REPLACE STAIRS & LANDING: FIELDHOUSE GOLF & DIVING GYMS 2/28/2008  
FIELDHOUSE NORTH ADDITION 08-01518 SOUTH & EAST & WEST DOORS: 2 PAIR OF 3-O X 7-O DOORS FIELDHOUSE 4/7/2008  
FINE ARTS 07-01021 STAGE RIGGING MAINTENANCE: A&S FINE ARTS 6/29/2007  
FINE ARTS 07-01022 IMPROVE CORRIDOR LIGHTING: FINE ARTS 6/29/2007  
FINE ARTS 08-01229 REMODEL: FINE ARTS PRACTICE ROOMS 8/20/2007  
FINE ARTS 08-01436 BUILD SHELVING UNIT TO STORE DRUMS: FINE ARTS 132 2/12/2008  
FOUNDATION HOUSE 08-01193 INSTALL DRYWALL: FOUNDATION HOUSE BASEMENT 7/31/2007  
FOUNDATION HOUSE 08-01448 CHANGE THE LIGHT FIXTURES FROM SQUARE TO ROUND: FOUNDATION HOUSE DINING ROOM 2/27/2008  
GENERAL STORAGE 08-01353 REPLACE FLOOR: SHIPPING & RECEIVING WAREHOUSE 11/6/2007 4/15/2008
GEOLOGY 07-01071 REPLACE CASE FRONTS: GEOLOGY MUSUEM 6/30/2007 7/31/2008
GEOLOGY 08-01171 REPLACE CEILING LIGHTS: GEOLOGY 313 & 314 7/18/2007  
GEOLOGY 08-01258 REMODEL: GEOLOGY 20 9/11/2007  
GEOLOGY 08-01259 REPLACE TILE FLOOR: GEOLOGY HALLWAYS ROOMS 20 TO 17 9/11/2007  
GEOLOGY 08-01260 REPLACE TILE PAINT INSTALL SHADE: GEOLOGY 17 9/11/2007  
GEOLOGY 08-01261 REPLACE TILE: GEOLOGY HALLWAYS UP THE STAIRS & FROM ROOM130 TO 135 9/11/2007  
GEOLOGY 08-01272 INSTALL REFRIGERATION UNIT FOR SEDIMENT CORES: GEOLOGY B025 9/18/2007  
GEOLOGY 08-01316 ELEVATOR ADA REQUIREMENTS & PUMP REPLACEMENT GEOLOGY 10/12/2007  
HALF ACRE GYMNASIUM 07-01012 REPLACE INFIELD HEATING SYSTEM: HALF ACRE 110 6/29/2007 5/16/2008
HALF ACRE GYMNASIUM 07-01025 WINDOW REPLACEMENT: HALF ACRE 6/29/2007  
HALF ACRE GYMNASIUM 07-01057 REMOVE AND REPLACE ROOF D: HALF ACRE 6/30/2007  
HALF ACRE GYMNASIUM 08-01458 REPLACE DRAIN PIPING AROUND PERIMETER OF POOL: HALF ACRE 2/28/2008 8/29/2008
HALF ACRE GYMNASIUM 08-01531 CONSTRUCT COUNTER IN THE NORTH LOBBY: HALF ACRE 4/11/2008  
HALF ACRE GYMNASIUM 08-01566 INSTALL EMERGENCY LIGHTING IN POOL: HALF ACRE 4/28/2008  
HALF ACRE GYMNASIUM 08-01671 RUN ELECTRICITY ON NORTH HALLWAY BETWEEN THE WELLNESS CENTER AND THE INFIELD 6/4/2008  
HEALTH SCIENCE LIVING HOUSE 08-01425 REPLACE HEATING SYSTEM: HSL HOUSE 1/29/2008 7/18/2008
HEALTH SCIENCES COMPLEX 08-01175 REMODEL INTO OFFICES: HEALTH SCI 288 7/20/2007  
HEALTH SCIENCES COMPLEX 08-01210 DESIGN OAK DISPLAY TO HANG BANNER: HEALTH SCIENCES 351C 8/7/2007  
HEALTH SCIENCES COMPLEX 08-01293 CREATE OFFICE & INSTALL BENCHES: HEALTH SCIENCES 595 10/5/2007  
HEALTH SCIENCES COMPLEX 08-01303 CONSTRUCT & INSTALL SLIDING DOORS TO COVER SHELVES: HEALTH SCIENCES COMPLEX 151 10/10/2007  
HEALTH SCIENCES COMPLEX 08-01441 BUILD WALL & INSTALL COMBINATION LOCK: HEALTH SCIENCES 446 2/12/2008  
HEALTH SCIENCES COMPLEX 08-01478 BUILD SHADOW BOXES: HEALTH SCI HALLWAY BY ROOM 364 3/13/2008  
HEALTH SCIENCES COMPLEX 08-01480 PROTECT WALL FROM CHAIR DAMAGE: HEALTH SCI 364 3/13/2008  
IT FACILITY 08-01558 20 HOURS OF TIME FOR ROOF INSTALLATION INSPECTION: NEW IT FACILITY 4/24/2008  
IT FACILITY 08-01711 ASSIST DE-ENERGIZE & ENERGIZE TRANSFORMER ITF 6/17/2008  
IVINSON 08-01666 FABRICATE A 1/2" THREADED BOLT TO 1 1/2 THREADED PIPE FOR A PROJECTOR CEILING MOUNT IVINSON 6/4/2008  
JACOBY GOLF COURSE CLUB HOUSE 08-01682 SECURITY SYSTEM JACOBY GOLF 6/6/2008  
JONAH FIELD 08-01419 EXTEND GOAL POSTS SOCCER & FOOTBALL FIELDS 1/23/2008  
KAPPA SIGMA HOUSE (HONORS) 08-01616 SWITCH GEAR HONORS HOUSE 5/13/2008  
KAPPA SIGMA HOUSE (HONORS) 08-01678 ISOLATE IRRIGATION FEEDING HONORS HOUSE FROM TUNNEL HONORS HOUSE 6/5/2008  
KNIGHT HALL 08-01180 REMOVE SINK TOILET AND ASSOCIATED PLUMBING: KNIGHT HALL 136 7/24/2007  
KNIGHT HALL 08-01382 DISCONNECT & RELOCATE UTILITIES TO FACILITATE WINDOW REPLACEMENT: KNIGHT HALL BASEMENT 12/10/2007  
KNIGHT HALL 08-01422 REPLACE BLINDS: KNIGHT HALL 109 1/28/2008  
KNIGHT HALL 08-01447 REPLACE 2 WINDOW BLINDS: KNIGHT HALL ROOMS 345 & 347 2/25/2008  
KNIGHT HALL 08-01543 TURN OFF WATER FOR MARSHALL CONSTRUCTION: KNIGHT HALL 4/16/2008  
KNIGHT HALL 08-01660 BASEMENT REMODEL RE-KEY KNIGHT 6/2/2008  
KNIGHT HALL 08-01663 RM 357 INSTALL CEILING FAN KNIGHT 6/3/2008  
KNIGHT HALL 08-01695 SIGNS FOR DOORS AT COUNSELING CENTER KNIGHT HALL 6/10/2008  
KNIGHT HALL 08-01709 RM 48A REMOVE PLUMBING KNIGHT HALL 6/17/2008  
KNIGHT HALL 08-01710 LOBBY HANG & MOUNT FLAT SCREEN TV KNIGHT HALL 6/17/2008  
LANDMARK SQUARE APTS SITE 08-01243 REROOF AND BUILD DORMERS: LANDMARK APTS 8/31/2007  
LANDMARK SQUARE APTS SITE 08-01463 INSTALL BOILERS: LANDMARK SQUARE APARTMENTS 2/28/2008 9/5/2008
LARAMIE LOCATIONS 08-01738 UTILITY DISCONNECT FOR HOUSE MOVING 468 N 13TH 6/25/2008  
LAW SCHOOL 08-01304 INSTALL COMPACT SHELVING: LAW LIBRARY BASEMENT 10/10/2007  
LAW SCHOOL 08-01617 LOCATE TUNNEL TOP & UNDERGROUND POWER LAW BLDG 5/13/2008  
MCINTYRE HALL 08-01168 REMODEL COORDINATOR APTS: ORR WHITE DOWNEY & MCINTYRE HALLS 7/18/2007  
MCWHINNIE HALL 08-01455 INSTALL FLOORING ON STAIRWAYS LANDINGS & HALLWAYS: MCWHINNIE HALL 2/27/2008  
MEMORIAL FIELDHOUSE 08-01640 SHOWER RM WALL PARTITIONS & REMOVE 2 DRINKING FOUNTAINS & COUNTERTOP CABINET MEMORIAL FIELDHOUSE 5/21/2008  
MEMORIAL FIELDHOUSE 08-01647 INSTALL DEDICATED CIRCUITS FOR 4 TREADMILLS FIELDHOUSE 5/30/2008  
OLD MAIN 08-01387 REMOVE & REPLACE 4 LIGHT FIXTURES: OLD MAIN 204 12/12/2007  
OLD MAIN 08-01652 ROOM SIGN AFFIXED TO ROOM 403 OLD MAIN 5/30/2008  
OLD MAIN 08-01694 TO ORDER AND INSTALL ADA TACTILE SIGNAGE OLD MAIN 6/10/2008  
PHYSICAL SCIENCES 08-01135 INSTALL SAFETY SHOWER: PHYSICAL SCI ROOM 8 7/3/2007  
PHYSICAL SCIENCES 08-01227 INSTALL A CONNECTION TO COMPRESSED AIR LINE: PHYSICAL SCI 301A 8/20/2007  
PHYSICAL SCIENCES 08-01284 INSTALL ELECTRICAL FOR INSTALLATION OF LAB RESEARCH EQUIPMENT: PHYSICAL SCI 236 219 & 208 9/26/2007  
PHYSICAL SCIENCES 08-01349 CREATE CUSTODIAL ZONE OFFICE IN SE CORNER: PHYSICAL SCIENCE 3RD FL 11/6/2007  
PHYSICAL SCIENCES 08-01384 INSTALL METAL DOORS FOR SECURITY UPGRADES: PHYSICAL SCI 20 12/10/2007  
PHYSICAL SCIENCES 08-01471 INSTALL ELECTRONIC SECURITY SYSTEM: PHYSICAL SCI ROOM 20 3/11/2008  
PHYSICAL SCIENCES 08-01472 INSTALL LOCKING CABINET FOR CHEMICAL STORAGE: PHYSICAL SCI ROOM 20 3/11/2008  
PHYSICAL SCIENCES 08-01687 DEMOLISH AND REPLACE NORTHWEST STAIRS PHYSICAL SCIENCE 6/9/2008  
PLANT SCIENCE GREENHOUSE 08-01199 FIX CONTROLS & CONTROL DEVICES: PLANT SCI GREEN HOUSE 8/1/2007  
PLANT SCIENCE GREENHOUSE 08-01204 PREPARE ROOM FOR 4 GROWTH CHAMBERS: PLANT SCIENCE GREENHOUSE RM 14 8/2/2007  
PLANT SCIENCE GREENHOUSE 08-01395 INSTALL FREEZER TEMPERATURE ALARMS: AG GREENHOUSE 12/19/2007  
PLANT SCIENCE GREENHOUSE 08-01437 INSTALL REVERSE OSMOSIS SYSTEM FOR WATERING: AG EX STATION GREENHOUSE 2/12/2008  
PLANT SCIENCE GREENHOUSE 08-01438 INSTALL BACKUP GENERATOR: AG EX STATION GREENHOUSE 2/12/2008  
POWER PLANT 1 08-01524 SUPPORT FOR DEMOLITION: OLD POWER PLANT 4/9/2008  
POWER PLANT 1 08-01557 DRAIN AND CAP FUEL LINES IN BOILERS BEFORE ABATEMENT BEGINS: OLD POWER PLANT 4/23/2008  
RED BUTTES RESEARCH LAB 08-01491 REPLACE OR REPAIR FILTER SYSTEM & RAILS ON THE TRENCH SYSTEM: RED BUTTES EFFLUENT ROOM 3/13/2008  
ROCHELLE ATHLETICS CENTER 08-01653 CONDUITS FOR WIRELESS ACCESS RAC & IPF 5/30/2008  
ROSS HALL 08-01464 REKEY BASEMENT: ROSS HALL 3/4/2008  
ROSS HALL 08-01554 INSTALL DEDICATED POWER LINE FOR COPY MACHINE: ROSS HALL ROOM 448 4/23/2008  
ROSS HALL 08-01686 RM 442 ABATE TILE ROSS HALL 6/9/2008  
SERVICE BUILDING 07-01082 REMOVE LEAKING UNDERGROUND TANK: SERVICE BLDG - FLEET SERVICES 6/30/2007  
SERVICE BUILDING 08-01519 ROOM 117 &119 MAJOR MAINT ITEMS: PAINT, REPLACE CARPET, ASBESTOS ABATEMENT SERVICE BUILDING (USE PROJECT #08-01517 FOR NON-MM ITEMS: FRONT OFFICE PARTITIONS, 117 DEMO, IT, REWIRING, SINK REMOVAL, PARTITIONS, FURNITURE) 4/7/2008  
SERVICE BUILDING 08-01517 ROOM 117 REMODEL: DEMO, IT, RE-WIRING, SINK REMOVAL, PARITITIONS, & FURNITURE. FRONT OFFICE PARTITIONS AND CARPET CLEANING. SERVICE BUILDING (USE PROJECT #08-01519 FOR MM ITEMS: PAINT, CARPET, ASBESTOS IN RMS 117 & 119) 4/7/2008  
SERVICE BUILDING 08-01696 REPLACE HAIL DAMAGED ROOFS SERVICE BLDG - CHEM STORAGE - ROCHELLE - FINE ARTS - UNION - JACOBY CLUB HOUSE - PSIS GREENHOUSE 6/10/2008  
SIGMA PHI EPSILON HOUSE 08-01265 INSTALLING A FIRE SUPPRESSION SYSTEM & REPAIR WATER DAMAGE: SIGMA PHI EPSILON: 9/13/2007  
SPANISH WALK APTS SITE 07-01112 RECONSTRUCT ROAD: SPANISH WALK 6/30/2007 8/1/2008
SPANISH WALK APTS SITE 08-01350 REMOVE LIGHT FIXTURES & WINDBREAKS AT ENTRANCES: SPANISH WALK APTS 11/6/2007  
STATE VET LAB (ADDITION) 08-01189 REPLACE ROOF FAN: VET SCIENCES 212: 7/31/2007  
STATE VET LAB (ADDITION) 08-01343 REPLACE EPOXY FLOORING SYSTEM: SVCL NECROPSY LAB 10/31/2007  
STATE VET LAB (ROUND BUILDING) 08-01358 INSTALL ELECTRICAL: STATE VET CHEM LAB 203G 11/6/2007  
STUDENT HEALTH 08-01572 REKEY VARIOUS ROOMS: STUDENT HEALTH 4/30/2008  
STUDENT HEALTH 08-01651 SHUT OFF MECHANICAL VALVES STUDENT HEALTH 5/30/2008  
STUDENT HEALTH 08-01718 TURN OFF WATER 6/18/08 STUDENT HEALTH 6/19/2008  
TELECOMM/CENTREX 08-01477 PAINT & CARPET: CENTREX EDIT 1 3/13/2008  
TELECOMM/CENTREX 08-01726 UPGRADE UPS SEE LARRY MCNERNEY FOR DETIALS CENTREX BLDG 6/20/2008  
TRACK STADIUM 08-01310 INSTALL LIGHTINGS SOCCER COMPLEX NORTH 40 TRACK COMPLEX 10/12/2007  
TRACK STADIUM 08-01318 SURVEY & MARK JAVELIN AREA OUTDOOR TRACK 10/15/2007  
TRACK STADIUM 08-01659 POLE VAULT CONCRETE PAD OUTDOOR TRACK 5/30/2008  
UW CAMPUS PROPERTY 07-01014 INSTALL SIGNS: UW OUTREACH AND EXT STATE 6/29/2007 10/31/2007
UW CAMPUS PROPERTY 07-01023 MODERNIZE ELEVATORS: CAMPUS 6/29/2007 10/15/2008
UW CAMPUS PROPERTY 07-01032 EXTERIOR DOOR REPLACEMENT: CAMPUS 6/30/2007 9/1/2008
UW CAMPUS PROPERTY 07-01034 ELEVATOR REPAIRS INTERNAL PPL: CAMPUS 6/30/2007 7/1/2008
UW CAMPUS PROPERTY 07-01062 REPLACE CARPET: CAMPUS 6/30/2007  
UW CAMPUS PROPERTY 07-01064 FY07-08 CONTRACT ROOF MAINTENANCE CAMPUS 6/30/2007  
UW CAMPUS PROPERTY 07-01089 REPAIR HVAC EQUIPMENT: CAMPUS 6/30/2007  
UW CAMPUS PROPERTY 07-01099 2007 STEAM SHUTDOWN: CAMPUS 6/30/2007 4/30/2008
UW CAMPUS PROPERTY 07-01107 REPLACE VALVES AT CHILLED H2O COIL: CAMPUS 6/30/2007 6/30/2008
UW CAMPUS PROPERTY 07-01121 ANNUAL PARKING LOT MAINTENANCE: CAMPUS 6/30/2007  
UW CAMPUS PROPERTY 08-01134 MOVE BUS STOP SHELTERS: VARIOUS 7/3/2007  
UW CAMPUS PROPERTY 08-01202 RELOCATE FUEL FACILITY: SOUTH OF CEP 8/2/2007  
UW CAMPUS PROPERTY 08-01233 ROOF MAINTENANCE FY08: RESIDENCE LIFE & DINING 8/21/2007  
UW CAMPUS PROPERTY 08-01234 ROOF MAINTENANCE FY08: SUMMIT VIEW APTS 8/21/2007  
UW CAMPUS PROPERTY 08-01256 MODIFY DRAINAGE: EAST CAMPUS 9/11/2007  
UW CAMPUS PROPERTY 08-01276 REMOVE MESSENGER STRAND FROM ROCKY MNT POWER POLES: FROM 15TH & WILLETT TO 30TH & GARFIELD CAMPUS 9/24/2007  
UW CAMPUS PROPERTY 08-01340 LOAD TEST EMERGENCY GENERATORS: CAMPUS 10/30/2007 6/1/2008
UW CAMPUS PROPERTY 08-01367 REPLACE IRRIGATION PUMPS: 30TH & WILLET NE CORNER 11/15/2007  
UW CAMPUS PROPERTY 08-01386 PLANT HEDGE: SOUTH OF NEW FUEL FACILITY 12/11/2007  
UW CAMPUS PROPERTY 08-01416 UPGRADE POWER REQUIREMENTS: PREXYS PASTURE 1/17/2008  
UW CAMPUS PROPERTY 08-01470 UW OUTDOOR ART DISPLAY: PREXYS PASTURE 3/7/2008 8/15/2008
UW CAMPUS PROPERTY 08-01503 ASBESTOS ABATEMENT 3/24/2008 12/15/2008
UW CAMPUS PROPERTY 08-01525 CEILING SYSTEM REPLACEMENT: ENGINEERING BIO SCIENCE PHY SCIENCE 4/9/2008  
UW CAMPUS PROPERTY 08-01544 LANDSCAPING & BUILDING EXTERIOR UPGRADES: LEWIS STREET 4/16/2008  
UW CAMPUS PROPERTY 08-01559 ASPHALT & CONCRETE 2008: CAMPUS 4/24/2008  
UW CAMPUS PROPERTY 08-01563 BARK BEETLE SPRAYING SPRING 2008: CAMPUS 4/25/2008 6/25/2008
UW CAMPUS PROPERTY 08-01597 PHASE 4 FOR INFRARED SCANNING OF ELECTRICAL/MECHANICAL EQUIPMENT CAMPUS 5/8/2008  
UW CAMPUS PROPERTY 08-01608 MOVES FOR THE TESTING CENTER TO KNIGHT~DSS OFFICES IN COE TO KNIGHT~ECTL TO ENGINEERING ON OR BEFORE THE WEEK OF MAY 27TH 5/9/2008  
UW CAMPUS PROPERTY 08-01620 SUMMER 2008 MM PAINTING AND ASBESTOS ABATEMENT 5/14/2008  
UW CAMPUS PROPERTY 08-01624 BUY AND INSTALL BIKE RACKS THROUGHOUT CAMPUS 5/15/2008  
UW CAMPUS PROPERTY 08-01639 REFURBISH POST & PANEL SIGNS CAMPUS 5/20/2008  
UW CAMPUS PROPERTY 08-01716 CONTRACTOR HIT PIPE 1720 SORORITY ROW 6/18/2008  
UW CAMPUS PROPERTY 08-01724 INSTALL CABINETS FOR REAL ESTATE OPERATIONS CAMPUS 6/20/2008  
UW INDOOR PRACTICE FACILITY 08-01548 INSTALL UNDERGROUND CONDUIT: INDOOR PRACTICE FACILITY 4/18/2008  
UW INDOOR PRACTICE FACILITY 08-01553 RELOCATE TREES AT BUSINESS TO: INDOOR PRACTICE FACILITY 4/22/2008  
UWNPSRC JOHNSON LODGE 08-01250 REMOVE & REPLACE ROOF: AMK RANCH JOHNSON LODGE & WELL HOUSE 8/31/2007 6/30/2008
VETERINARY SCIENCES SITE 08-01370 EVALUATE HVAC SYSTEM: WSVL 11/26/2007  
VETERINARY SCIENCES SITE 08-01569 REPLACE MEDICAL AIR COMPRESSOR IN PENTHOUSE VET LAB 4/29/2008 8/15/2008
VETERINARY SCIENCES SITE 08-01585 REPLACE WATER CONDITIONING EQUIPMENT VET LAB 5/5/2008  
VETERINARY SCIENCES SITE 08-01634 MOUNT PROJECTOR, ELECTRIC TO PROJECTOR AND LOW VOLTAGE CABLING TO PODIUM VET LAB 5/19/2008  
VETERINARY SCIENCES SITE 08-01643 REMOVE BOILER UNDERGROUND STORAGE TANK STEVE VET CHEM LAB 5/28/2008  
VETERINARY SCIENCES SITE 08-01673 INSTALL NEW 208V CIRCUIT ON WEST WALL OF ROOM 203I VET LAB 6/5/2008  
WAINWRIGHT BUNGALOWS WEST BLDG 08-01688 REPLACE HEATING & VENTILATING IN PRINT SHOP & CERAMICS STUDIO WAINWRIGHT BUNGALOWS 6/9/2008  
WASHAKIE CENTER 08-01254 REPLACE ROLLING DOOR WITH 2 CARD SWIPE DOORS: WASHAKIE CENTER DINING SERVICES STORAGE AREA 8/31/2007  
WASHAKIE CENTER 08-01286 INSTALL WINDOW: WASHAKIE CNTR OUTSIDE OFFICE 25G 9/26/2007  
WHITE HALL 08-01432 INSTALL CARD SWIPE: WHITE HALL NORTH DOORS 2/7/2008  
WIRO OBSERVATORY SITE 08-01417 CONSTRUCT RESTROOM FOR GARAGE JELM MTN OBSERVATORY 1/23/2008  

 

 