Meritorious Applications (continued)
Interactive Real Time Electric Power Allocation
The electric power industry is rapidly getting immersed in the information age
as a result of congressional legislation and a notice of proposed rulemaking
issued by the Federal Energy Regulatory Commission, all aimed at promoting
wholesale competition through non-discriminatory open transmission access, i.e.,
deregulation. Much of the impact of deregulation takes on a regional or even
international dimension as utilities seek to operate large scale power grids in
the most efficient engineering and economic mode possible. Many of the leading
electric utilities are already involved in transactions based on real time
information transmitted through an electronic information network over the
Internet. The network, called the transmission services information network, or
TSIN, allows access by all authorized users anywhere in the world and provides
current information on the available transmission capacity (ATC), cost and tariffs
for transmission capacity, and cost of ancillary services, such as spinning
reserves and reactive support. The ATC is calculated as the difference between the
total transfer capability (TTC) and the firm commitments along the transmission
corridor. Although the firm commitments can be easily found, the TTC is a quantity
that can not be calculated easily. The latter is defined as being equivalent to
the first-contingency total transfer capability and is usually limited by thermal
or stability limits on the transmission interface. The term "first
contingency" refers to outage of a single element, such as a generator, a
transmission line, a transformer, and so forth which are integral parts of a power
grid. Since the power system is dynamic, the system will continuously settle into
new equilibria based on various post-outage conditions. On most occasions, this
post-disturbance equilibrium point will be stable, meaning that the system
frequency will be retained at or close to nominal. However, occasionally, the
system can reach an unstable equilibrium point because of inadequate transfer
capability or inadequate var support. Two most recent examples of system-wide
blackout were the July and August 1996 disturbances in the western US grid. Fig. 1
shows the layout of the interconnected system in the Western United States and
Canada comprised of more than 20 different electric utility companies in 10 states
and two Canadian provinces.

Figure 1. A map of the 500 kV main transmission grid in Western
US
Identifying these severe and harmful contingencies, by exhaustively going
through a list of contingencies, even on an off-line basis, is very time-consuming
and computationally intensive. Each contingency analysis (out of a list of
thousands) emphasizing system dynamics that require solving non-linear
differential equations may take CPU times in excess of a minute on UW’s fastest
computers. Naturally, performing full-scale contingency analysis, on-line at even
close to real time, for power grids containing more than 5,000 nodes and 10,000
branches is still not possible without resorting to supercomputers. Therefore, for
a massively interconnected network such as the Western Systems Coordinating
Council (WSCC) grid of Fig. 1, performing accurate, on-line ATC calculations and
posting those on the Internet would not be possible without high-speed connections
to supercomputing centers, coupled with low-latency feedback across the network.
Such a capability will maximize the economics of power transfers between two or
more control areas of a power system. An illustration of a lack of fast, secure
communication among the control area entities is in the August 1996 outage of the
western grid. The initiating fault event was merely a tree touching a high voltage
transmission line in Wyoming that caused a short circuit in that line. However,
this event cascaded into a series of outages because of excessive power demand in
load areas such as California and Idaho. Long before a "point of no
return" was reached, two major power lines in the Pacific Northwest had been
lost. Yet, system operators in California were unaware of the growing problem and
kept on importing power from northern western hydro plants without increasing
backup generation in local areas. Therefore, ways to provide real time data
sharing among control centers automatically is a necessity in the face of this
ever-growing complexity in interconnected power grid operation.
ATC calculation is only one example of a need for high-speed Internet
connection in the area of power systems operation. Many progressive electrical
utilities are now developing comprehensive data acquisition facilities. The
emerging critical path challenge is to extract essential information from this
data and to distribute the pertinent information where and when it is needed over
very wide spread geographical locations. The uses of a high performance Internet
connection could range from the basic tasks of remote data storage and shared
retrieval to the remote near real time applications of power system monitoring and
control. Information sharing between utilities accomplished in near real time on a
high speed Internet connection could have a tremendous impact on the efficient and
reliable use of the system. Again, these issues were brought into sharp focus by
the power outages experienced by the Western US grid in the summer of 1997. Post
analysis of monitoring records from these disturbances [2] provided many
indications of potential problems. If this analysis could have been performed in
near real time and distributed to the appropriate user, the system's vulnerability
could have been realized prior to the power outage.
Currently the University of Wyoming (Department of Electrical Engineering) is
working with Bonneville Power Administration (BPA), Pacific Northwest National
Laboratory (PNNL), and the Electric Power Research Institute (EPRI) on developing
methods for monitoring the stability of an interconnected power system in near
real time [3]. For example, the Western United States and parts of Canada have a
large interconnected power system with data acquisition systems spread at several
key locations throughout the system [4]. The amount of data and the great
distances involved between monitoring stations will require a high performance
network to manage and share all the data. For instance, the Dittmer Control
Center, Vancouver, Washington collects over 96 channels of data. With fast
Internet access this data could be shared among users throughout the system. The
DOE-funded Wide Area Measurement System (WAMS) program foresees use of a high
performance connection to the Internet in this manner. Possible future uses of
this monitoring network involves the area of automated control technology.
Development of prototype models, such as ADAPT at UW, as well as software, and
technologies which address the problems described above require additional
bandwidth and low-latency connections for "real world" testing of
systems being perfected at the University of Wyoming.
previous | next