2008 Capital Construction Information


PowerPoint File  Drawings

 

INFORMATION TECHNOLOGY FACILITY
(Anticipated Construction = 16 Months)

May 19 – June 6, 2007 Honors House abatement
June 5, 2007 Final Guaranteed Maximum Price, materials ordered.
August 6, 2007 Construction Mobilization
August 6, 2007 Closure of Sorority Road & East Green
Summer 2008 Chilled Water Construction on Sorority Road and across Frat Mall
December 2008 Building Construction Completion
December 2008 Open all Sorority Road
Dec. 08 – June 2009 Installation and testing of Central Computing
Dec. 08 – June 2009 Information Technology Dept. Move-in
   
Parking Data 145 Parking Spaces Permanently removed Crane/Hill Lot – 211 Remaining (Frisbee = 345)
  50 Temporarily removed Sorority Road – 397 remaining

 

INFORMATION LIBRARY AND LEARNING CENTER
(Anticipated Construction = 24 – 27 Months)
 

July 23, 2007 - Aug 1, 2009 Union Parking Lot Portion & Union Alley Closed.
Sept 1, 2007 Construction Start
May 15 - August 15, 2008 13th Street Closure
Sept 1, 2009 Building Construction Completion
Sept– Dec 2009 Complete installation of furnishings
   
Parking Data 114 Temporarily removed Union Parking Lot – 238 remaining

 

Day Lot = 137 spaces          Shuttle Lot = 454 Spaces                Long term = 66 Spaces